Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1304460.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,641.00
Current Penalty: $0.00
Issuance Date: 04/24/2018
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 06/29/2018
Gravity: 10
Report ID: 0112600
Contest Date:
Final Order: 05/21/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/21/2018 | $0.00 | 06/29/2018 | Serious | |
| Penalty | Z: Issued | 04/24/2018 | $11,641.00 | 06/11/2018 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: 100 Simplex Dr, Westminster, MA On March 27, 2018 at the start of the inspection, the employer had not performed a periodic inspection that ensured each procedure was inspected for inaccuracies during an actual energy control task and did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure.