Violation Detail
Standard Cited: 19100132 A General requirements.
Inspection Nr: 1019759.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/29/2015
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 5
Report ID: 0317500
Contest Date:
Final Order: 06/15/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/15/2015 | $0.00 | Serious | ||
| Penalty | Z: Issued | 05/29/2015 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.132(a): Protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, was not provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards of processes or environment, chemical hazards, radiological hazards, or mechanical irritants encountered in a manner capable of causing injury or impairment in the function of any part of the body through absorption, inhalation or physical contact: a) Job site, 650 Braddock Avenue, Pittsburgh, PA: On or about January 17, 2015, during production activities, the employer did not ensure that fall protection systems/devices were used while employees were up on the top of the EDF Hi-Storm unit under construction, exposing employees to fall hazards of up to approximately 15 feet.
Translate