Violation Detail
Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
Inspection Nr: 935934.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $5,000.00
Issuance Date: 11/01/2013
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 11/21/2013
Gravity:
Report ID: 0523400
Contest Date:
Final Order: 11/26/2013
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/26/2013 | $5,000.00 | 11/21/2013 | Other | |
| Penalty | Z: Issued | 11/01/2013 | $0.00 | 11/21/2013 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): (a) On or about August 27, 2013 at the 700 E. Jones Street, Milwaukee, Wisconsin Preliminary Treatment Building, all energy sources for the Exhaust Fan 7-1 were not locked, blocked, and tagged to render all moving parts inoperative. An employee was exposed to amputation hazards from a moving belt.