Violation Detail
Standard Cited: 19260451 C02 IV General requirements.
Inspection Nr: 907446.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $2,000.00
Current Penalty: $2,000.00
Issuance Date: 06/26/2013
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): C
Gravity: 5
Report ID: 0134000
Contest Date:
Final Order: 07/10/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/10/2013 | $2,000.00 | Serious | ||
Penalty | Z: Issued | 06/26/2013 | $2,000.00 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.451(c)(2)(iv): Front-end loaders and similar pieces of equipment shall not be used to support scaffold platforms unless they have been specifically designed by the manufacturer for such use. (a) Location - 19 Commerce Way, Woburn, MA: On or about 5/17/2013, an employee was working from a makeshift scaffold work platform that was not attached to the forks of a powered industrialized truck.