Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 904225.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/23/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/28/2013
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 06/13/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/13/2013 | $0.00 | 07/28/2013 | Serious | |
| Penalty | Z: Issued | 05/23/2013 | $0.00 | 07/28/2013 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard were being followed: (a) Precision Cut Industries, Incorporated - The employer did not conduct an internal audit to ensure de-energization procedures were being properly implemented, on or about May 2, 2013. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.