Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1826351.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/24/2025
Nr Instances: 2
Nr Exposed: 2
Abatement Date: 04/01/2026
Gravity: 5
Report ID: 0521700
Contest Date:
Final Order: 08/15/2025
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | 12/18/2025 | $0.00 | 04/01/2026 | Serious | |
| Penalty | I: Informal Settlement | 08/15/2025 | $0.00 | 09/10/2025 | Serious | |
| Penalty | Z: Issued | 07/24/2025 | $0.00 | 09/10/2025 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed. a.) Mill Area - On or about February 6, 2024, employees performed the service and maintenance task of replacing the Hopper 1 augers. The employer did not ensure periodic inspections of the energy control procedures were performed at least annually as required by the standard. b.) Mill Area - On or about May 8, 2025, employees performed the service and maintenance task of repairing the Borger RR 6000 macerator. The employer did not ensure periodic inspections of the energy control procedures were performed at least annually as required by the standard.