Violation Detail
Standard Cited: 19100333 B02 Selection and use of work practices
Inspection Nr: 1801384.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/17/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 04/30/2025
Gravity: 5
Report ID: 0112300
Contest Date:
Final Order: 04/02/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/02/2025 | $0.00 | 04/30/2025 | Serious | |
| Penalty | Z: Issued | 03/17/2025 | $0.00 | 04/30/2025 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.333(b)(2): While an employee was exposed to contact with parts of fixed electric equipment or circuits which were deenergized, the circuits energizing the parts were not locked out or tagged or both in accordance with the requirements of this paragraph (b) of 29 CFR 1910.333(b)(2). a) Worksite: On or about January 31, 2025, employees were exposed to electrical shock and burn hazards while performing electrical maintenance activities without the use of proper Lockout/Tagout equipment.