Violation Detail
Standard Cited: 19100147 F01 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1786655.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,768.00
Current Penalty: $0.00
Issuance Date: 04/30/2025
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 05/19/2025
Gravity: 5
Report ID: 0215800
Contest Date: 05/23/2025
Final Order: 08/08/2025
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/08/2025 | $0.00 | 05/19/2025 | Other | |
| Penalty | C: Contested | 06/13/2025 | $12,768.00 | 05/19/2025 | Serious | |
| Penalty | Z: Issued | 04/30/2025 | $12,768.00 | 05/19/2025 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
1910.147(f)(1)(ii) When lockout or tagout devices temporarily were removed from the energy isolating device and the machine or equipment was energized to test or position the machine, the employees were not removed from the machine or equipment area in accordance to the paragraph (e)(2): a) On or about 11/5/2024, Production Area: Lockout/Tagout energy control procedures were not utilized by employees who performed servicing and maintenance tasks including, but not limited to, inspecting the sensors of the Sumitomo Injection Molding Machine. Abatement certification required for this item.