Violation Detail
Standard Cited: 19100147 D04 III B The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1781450.015
Citation: 01001B
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/10/2025
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 05/12/2025
Gravity: 10
Report ID: 0626700
Contest Date: 05/05/2025
Final Order: 02/09/2026
Related Event Code (REC): A
Emphasis:
Substance: 1480
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 02/09/2026 | $0.00 | 05/12/2025 | Serious | |
| Penalty | C: Contested | 05/05/2025 | $0.00 | 05/12/2025 | Serious | |
| Penalty | Z: Issued | 04/10/2025 | $0.00 | 05/12/2025 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(d)(4)(iii)(B): Where a tag could not be affixed directly to the energy isolating device, the tag was not located as close as safely possible to the device, in a position that would have been immediately obvious to anyone attempting to operate On or about October 10, 2024, in ARU #6/7 at Deer Park Refinery Limited located in Deer Park, TX, the host employer (DPRL) failed to affix tag(s) on the energy isolation device for 12-inch CAG header and /or flare lines in ARU#6/7.