Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1689778.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,656.00
Current Penalty: $0.00
Issuance Date: 11/06/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 06/28/2024
Gravity: 10
Report ID: 0316300
Contest Date:
Final Order: 12/04/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/04/2023 | $0.00 | 06/28/2024 | Other | |
Penalty | Z: Issued | 11/06/2023 | $12,656.00 | 11/17/2023 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(4)(ii)(B): Specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy had not been put into place. Location: 100 Emancipation Dr. Hampton Va. On or about: 17 June 2023. a) Employees performed an electrical air-switch repair for Veterans Medical Center Buildings (B148), the air switch was not effectively de-energized. Procedures were not clearly outlined to control hazardous energy.