Standard Cited: 19260651 B04 Specific Excavation Requirements.
Inspection Nr: 1657770.015
Citation: 01001B
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $13,750.00
Issuance Date: 09/15/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 10
Report ID: 0317300
Contest Date:
Final Order: 10/20/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/20/2023 | $13,750.00 | Other | ||
Penalty | Z: Issued | 09/15/2023 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.651(b)(4): While the excavation was opened, underground installations were not protected, supported or removed as necessary to safeguard employees: a) On the roadway in front of18193 Huff Road, Milton, DE 19968: On or about March 20, 2023, employees were required to work in the excavation with unprotected and ungrounded buried electrical lines that were exposed once the area was excavated. The power lines were energized and ran from one side of the excavation to the other side of the excavation exposing employees to shock/electrocution hazards.