Violation Detail
Standard Cited: 19100029 B02 Fall protection systems and falling object protection-criteria and practices.
Inspection Nr: 1608899.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 11/15/2022 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/19/2022
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0316300
Contest Date:
Final Order: 11/15/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/15/2022 | $0.00 | 11/15/2022 | Serious | |
Penalty | Z: Issued | 10/19/2022 | $0.00 | 11/15/2022 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.29(b)(2): The employer did not ensure that guardrail systems met the requirement that mid-rails, screens, mesh, intermediate vertical members, solid panels, or equivalent intermediate members that are installed between the walking-working surface and the top edge of the guardrail system as follows when there is not a wall or parapet that is at least 21 inches (53 cm) high: a) Building #1 Pipe/Weld shop: On or about 07/20/2022, a section of middle railing along the edge of the mezzanine was missing thereby exposing employees to a possible 10ft fall hazard. b) Building #3 loading dock: On or about 07/20/2022, a section of middle railing was missing thereby exposing employees to a possible 4ft fall hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.