Violation Detail
Standard Cited: 19100269 D02 VI Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1591289.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $8,000.00
Issuance Date: 10/06/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/13/2023
Gravity: 10
Report ID: 0112300
Contest Date: 10/31/2022
Final Order: 06/12/2023
Related Event Code (REC): I;R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 06/12/2023 | $8,000.00 | 07/13/2023 | Other | |
| Penalty | C: Contested | 11/01/2022 | $0.00 | 11/01/2022 | Serious | |
| Penalty | Z: Issued | 10/06/2022 | $0.00 | 11/01/2022 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.269(d)(2)(vi): The employer did not provide training to ensure that the purpose and function of the energy control program were understood by employees and that the knowledge and skills required for the safe application, usage, and removal of energy controls were acquired by employees: (a) Manchester Street Station - Generator #10: On or about 4/21/2022, the employer did not provide adequate training to ensure that the purpose and function of the energy control program were understood by employees, in that the employees altered and or deviated from lockout/tagout procedures, and connected the system ground to a neutral bus bar and not the correct ground point.