Violation Detail
Standard Cited: 19100252 A03 II General requirements.
Inspection Nr: 1545863.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/29/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/26/2021
Gravity: 5
Report ID: 0317500
Contest Date:
Final Order: 10/22/2021
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/22/2021 | $0.00 | 10/26/2021 | Serious | |
Penalty | Z: Issued | 09/29/2021 | $0.00 | 10/26/2021 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.252(a)(3)(ii): All hollow spaces, cavities, or containers were not vented to permit the escape of air or gases before preheating, cutting, or welding was performed: a) At the facility, on or about July 23, 2021- A hydraulic tank on the vehicle was not vented to permit the escape of air or gases before welding was performed. An employee received 2nd and 3rd degree burns on the arm and neck when welding on a hydraulic tank resulting from a flash that occurred.