Violation Detail
Standard Cited: 19260651 J02 Specific Excavation Requirements.
Inspection Nr: 1436545.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/16/2020
Nr Instances: 2
Nr Exposed: 4
Abatement Date: 03/20/2020
Gravity: 10
Report ID: 0830300
Contest Date: 03/18/2020
Final Order: 03/03/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 03/03/2021 | $0.00 | 03/20/2020 | Serious | |
| Penalty | C: Contested | 06/11/2020 | $0.00 | 03/20/2020 | Serious | |
| Penalty | Z: Issued | 03/16/2020 | $0.00 | 03/20/2020 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary: (a) On or about October 8, 2019, for the employees exposed to struck-by hazards while installing water supply pipe in a trench where a large spoil pile was on the edge of the trench, for the water transmission line 19-01 project, in the vicinity of 58+50 to STA 59+60, near the intersection of 66th Street SE & Apple Creek Road in Bismarck, North Dakota. (b) On or about October 9, 2019, and at times prior, for the employees exposed to struck-by hazards while installing water supply pipe in a trench where a large spoil pile ran the full length of the trench less than 1 foot away from the edge, for the water transmission line 19-01 project, in the vicinity of STA 65+47, near the intersection of 66th Street SE & Apple Creek Road in Bismarck, North Dakota.
Translate