Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1429632.015
Citation: 01001B
Citation Type: Other
Abatement Date: 3
Initial Penalty: $11,934.00
Current Penalty: $0.00
Issuance Date: 12/19/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0626300
Contest Date:
Final Order: 01/14/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/14/2020 | $0.00 | Other | ||
Penalty | Z: Issued | 12/19/2019 | $11,934.00 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed: a) On or about August 30, where the employer did not ensure that energy control procedures for the CIP system were conducted at least annually or corrected if there are deviations or inadequacies identified with flow issues.