Violation Detail
Standard Cited: 19100022 D01 General requirements.
Inspection Nr: 1400452.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/13/2019
Nr Instances: 3
Nr Exposed: 11
Abatement Date: 11/25/2019
Gravity: 1
Report ID: 0215800
Contest Date: 11/21/2019
Final Order: 10/14/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 10/14/2021 | $0.00 | 11/25/2019 | Serious | |
| Penalty | C: Contested | 11/22/2019 | $0.00 | 11/25/2019 | Serious | |
| Penalty | Z: Issued | 11/13/2019 | $0.00 | 11/25/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.22(d)(1): Walking-working surfaces were not inspected, regularly, and maintained in a safe condition.: a) Shakeout Area, on or about 5/15/19: Walking-working surfaces near the accumulation table and corner of M23 had wooden pallets on the floor. b) Muller Deck, on or about 7/31/19: Final Stair before the Pent House Deck had an air line hose lying on the floor in front of the stairs and on the bottom 2 steps. c) E-Melt Basement Area, on or about 9/17/19: Main Electrical Room had an uneven floor due to broken metal grates.