Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1399934.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/12/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 09/06/2019
Gravity: 5
Report ID: 0213100
Contest Date:
Final Order: 09/09/2019
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/09/2019 | $0.00 | 09/06/2019 | Serious | |
| Penalty | Z: Issued | 08/12/2019 | $0.00 | 09/06/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Facility - On or about August 1, 2019, the employer did not conduct a periodic inspection within the last 12 months for performing servicing and/or maintenance work on the Line 52 Winder. The last periodic inspection was performed on 2/23/18.
Translate