Violation Detail
Standard Cited: 19100219 E02 I Mechanical power-transmission apparatus.
Inspection Nr: 1370996.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 05/02/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/12/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0215800
Contest Date:
Final Order: 04/22/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/22/2019 | $0.00 | 05/02/2019 | Serious | |
Penalty | Z: Issued | 04/12/2019 | $0.00 | 05/02/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.219(e)(2)(i): Overhead horizontal belt(s) with lower parts seven -7 feet or less from the floor(s) or platform(s) were not guarded on the sides and bottom in accordance with the requirements specified at CFR 1910.219(o)(3): a. At the conveyor belt "54 merge", on or about 1/11/19: A section of overhead horizontal belt at the pulley was not guarded against accidental contact. Abatement certification must be submitted for this item.