Violation Detail
Standard Cited: 19100147 C07 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1359183.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/18/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/16/2020
Gravity: 10
Report ID: 0418300
Contest Date: 04/11/2019
Final Order: 01/15/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 01/15/2020 | $0.00 | 03/16/2020 | Other | |
| Penalty | C: Contested | 04/15/2019 | $0.00 | 04/11/2019 | Serious | |
| Penalty | Z: Issued | 03/18/2019 | $0.00 | 04/11/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(7)(i): The employer did not provide adequate training to ensure that the purpose and function of the energy control program was understood by employees: (a) On or about 11/01/2018 - Reman Department, the employer did not provide adequate training to employees who cleared jammed material at the Panel Machine.
Translate