Violation Detail
Standard Cited: 19100146 D05 I Permit-required confined spaces
Inspection Nr: 1344064.015
Citation: 01001B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/14/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/04/2019
Gravity:
Report ID: 0830600
Contest Date:
Final Order: 01/10/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/10/2019 | $0.00 | 01/04/2019 | Other | |
Penalty | Z: Issued | 12/14/2018 | $0.00 | 01/04/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.146(d)(5)(i): Under the permit required confined space program required by 29 CFR 1910.146(c)(4), the employer did not evaluate permit space conditions when entry operations were conducted by testing conditions in the permit space to determine if acceptable entry conditions existed before entry was authorized to begin: a) On or about August 14, 2018, and at times prior, the employer, Tolin Mechanical Systems Company, did not ensure atmospheric testing was conducted in the permit-required confined space (underground pump vault) so as to determine if entry conditions were acceptable before employees were required to enter the space. Abatement Note: Abatement certification and documentation are required for this item (see enclosed Sample Abatement-Certification Letter).