Standard Cited: 19100219 C03 Mechanical power-transmission apparatus.
Inspection Nr: 1334779.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/17/2018
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 08/23/2018
Gravity: 5
Report ID: 0317000
Contest Date:
Final Order: 08/29/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/29/2018 | $0.00 | 08/23/2018 | Serious | |
| Penalty | Z: Issued | 08/17/2018 | $0.00 | 08/23/2018 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.219(c)(3): Vertical or inclined shafting seven -7 feet or less from floor or working platform was not enclosed with stationary casing: a) Water Ice Production Room - The employer did not ensure that all vertical shafting leading to the augers in the flavor mixing tanks were properly guarded exposing the employees to amputation hazards. Observed on or about 08 JULY 2018.