Violation Detail
Standard Cited: 19100119 D03 I D Process safety management of highly hazardous chemicals.
Inspection Nr: 1247176.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/11/2018
Nr Instances: 1
Nr Exposed: 28
Abatement Date: 02/26/2018
Gravity: 10
Report ID: 0214200
Contest Date: 02/01/2018
Final Order: 08/20/2018
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/20/2018 | $0.00 | 02/26/2018 | Serious | |
Penalty | C: Contested | 02/01/2018 | $0.00 | 02/26/2018 | Serious | |
Penalty | Z: Issued | 01/11/2018 | $0.00 | 02/26/2018 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.119(d)(3)(i)(D): Information pertaining to equipment in the process did not include relief system design and design basis: a) Building 2, vanilla area The employer did not compile PSI that was specific to design and design basis for pressure safety valves on vanilla box extractors 40-42 and concentrators 45-47. Violation occurred on or about 7/13/17.