Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1208185.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $5,387.00
Issuance Date: 05/08/2017
Nr Instances: 1
Nr Exposed: 43
Abatement Date: 11/15/2017
Gravity: 5
Report ID: 0830500
Contest Date: 05/31/2017
Final Order: 12/27/2017
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/27/2017 | $5,387.00 | 11/15/2017 | Serious | |
| Penalty | C: Contested | 06/06/2017 | $0.00 | 06/12/2017 | Serious | |
| Penalty | Z: Issued | 05/08/2017 | $0.00 | 06/12/2017 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed: (a) Servtech at 333 Centennial Pkwy. Louisville, CO: On or before 1/19/2017, the employer had not conducted periodic inspections of all energy control procedures including but not limited to the Drill-Line CNC hole cutting machine (Ocean Machinery, Model: MDL-1000/1C, Custom Avenger 40, SN: A002943), to ensure all energy sources capable of causing injury are isolated and rendered inoperative prior to servicing and or maintenance. This condition exposed employees to amputation hazards.