Violation Detail
Standard Cited: 19260451 H01 General requirements.
Inspection Nr: 1203691.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 03/10/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/06/2017
Nr Instances: 2
Nr Exposed: 8
Related Event Code (REC):
Gravity: 1
Report ID: 0627500
Contest Date:
Final Order: 03/01/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/01/2017 | $0.00 | 03/10/2017 | Serious | |
Penalty | Z: Issued | 02/06/2017 | $0.00 | 02/16/2017 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.451(h)(1): Each employee on a scaffold was not provided with additional protection from falling hand tools, debris, and other small objects through the installation of toeboards, screens, guardrail systems, or through the erection of debris nets, catch platforms, or canopy structures that contained or deflected the falling objects: On or about January 18, 2017 the employer did not ensure that toeboards were installed on scaffolding when employees were engaged in plastering operations. This condition exposed employees to struck-by hazards.