Standard Cited: 19100269 D08 IV Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1102415.015
Citation: 01001B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/26/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/13/2016
Gravity: 5
Report ID: 0418200
Contest Date: 05/16/2016
Final Order: 03/31/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/31/2017 | $0.00 | 06/13/2016 | Serious | |
Penalty | C: Contested | 05/20/2016 | $0.00 | 06/13/2016 | Serious | |
Penalty | Z: Issued | 04/26/2016 | $0.00 | 06/13/2016 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.269(d)(8)(iv): Whenever outside servicing personnel are to be engaged in activities covered by paragraph (d) of this section, the on-site employer and the outside employer shall inform each other of their respective lockout or tagout procedures, and each employer shall ensure that his or her personnel understand and comply with restrictions and prohibitions of the energy control procedures being used. a. Plant Bowen, JBR 3/4 Building - Prior to performing electrical circuit modification work using Georgia Power Company clearance procedures, Georgia Power Company and ABB, Inc. did not inform each others employee representatives of their respective lockout or tagout program, procedures and policies to ensure each employee understood and complied with the restrictions and prohibitions of the energy control procedures being used.