Standard Cited: 19260451 C02 IV General requirements.
Inspection Nr: 994627.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,200.00
Current Penalty: $1,320.00
Issuance Date: 03/02/2015
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 03/10/2015
Gravity: 5
Report ID: 0316400
Contest Date: 03/26/2015
Final Order: 05/18/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/18/2016 | $1,320.00 | 03/10/2015 | Serious | |
Penalty | C: Contested | 04/02/2015 | $2,200.00 | 03/10/2015 | Serious | |
Penalty | Z: Issued | 03/02/2015 | $2,200.00 | 03/10/2015 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(c)(2)(iv): Front-end loaders and similar pieces of equipment are used to support scaffold platforms when they are not specifically designed by the manufacturer for such use: (a) Suncrest: The employer uses a forklift to support a scaffold platform when the forklift is not specifically designed by the manufacturer for such use. This condition was most recently observed on or about September 3, 2014, when a piece of plywood was laid on top of the forks of a Pettibone forklift, Model 8044, and used as a scaffold platform for an employee applying tape to the house wrap approximately 25 feet above the ground.