Violation Detail
Standard Cited: 19100333 C03 Selection and use of work practices
Inspection Nr: 980269.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 10/02/2014
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/24/2014
Gravity: 10
Report ID: 0627510
Contest Date:
Final Order: 11/05/2014
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/05/2014 | $7,000.00 | 11/24/2014 | Serious | |
| Penalty | Z: Issued | 10/02/2014 | $7,000.00 | 10/08/2014 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.333(c)(3): When work was to be performed near overhead lines, the lines were not de-energized and grounded, nor were other protective measures provided before work was started: On or about June 09, 2014, at the University Brittany Lease #39063, the employer did not ensure overhead power lines were de-energized prior to an employee raising the boom on a water service truck. This condition exposes employees to electrical shock and electrocution hazards.