Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 500278.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,300.00
Current Penalty: $6,300.00
Issuance Date: 12/31/2012
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 01/28/2013
Gravity: 10
Report ID: 0418100
Contest Date:
Final Order: 01/24/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 12/31/2012 | $6,300.00 | 01/28/2013 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit On or about July 3, 2012: (a) Employees were engaged in the installation of electrical equipment to provide power to space heaters used to regulate condensation within the switchgear cabinet located within a substation, were exposed to electrical shock and arc flash hazards. As employer failed to establish through inquiry, direct observation or testing that electrical equipment was energized.