Standard Cited: 19100107 B01 Spray finishing using flammable and combustible materials.
Inspection Nr: 1808462.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $6,620.00
Current Penalty: $3,972.00
Issuance Date: 07/01/2025
Nr Instances: 1
Nr Exposed: 7
Abatement Date:
Gravity: 5
Report ID: 0418100
Contest Date:
Final Order: 08/27/2025
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/27/2025 | $3,972.00 | Serious | ||
Penalty | Z: Issued | 07/01/2025 | $6,620.00 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.107(b)(1): The spray booth�was not�substantially constructed�of steel,�securely and�rigidly supported,�or of�concrete or�masonry. a) Painting Area: On or about 2/28/2025, and at times prior, the employer exposed employees to respiratory and fire hazards in that the inflatable paint booth was not constructed�of steel and securely supported inside of the building while employees used it for painting operation.