Violation Detail
Standard Cited: 19260451 A01 General requirements.
Inspection Nr: 1779689.015
Citation: 01001A
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,895.00
Current Penalty: $14,895.00
Issuance Date: 03/25/2025
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 04/04/2025
Gravity: 10
Report ID: 0626700
Contest Date: 04/11/2025
Final Order:
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 06/12/2025 | $14,895.00 | 04/04/2025 | Serious | |
Penalty | Z: Issued | 03/25/2025 | $14,895.00 | 04/04/2025 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(a)(1): Each scaffold and/or scaffold component was not capable of supporting, without failure, its own weight and at least 4 times the maximum intended load applied or transmitted to it: a) On or about October 3, 2024, at a tank construction site, employees operated mobile scaffolds whose support components did not support at least 4 times the maximum intended load while employees were setting up to perform welding activities.