Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1727109.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $14,518.00
Current Penalty: $13,670.00
Issuance Date: 05/01/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/31/2024
Gravity: 10
Report ID: 0112600
Contest Date:
Final Order: 05/28/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/28/2024 | $13,670.00 | 07/31/2024 | Serious | |
| Penalty | Z: Issued | 05/01/2024 | $14,518.00 | 06/18/2024 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: 2355 Providence Road, Northbridge, MA: On and before February 9, 2024, employees performed maintenance and servicing activities on Molding Press #9 without a documented energy control procedure to direct the control of potentially hazardous energy.