Violation Detail
Standard Cited: 19100268 B07 Telecommunications.
Inspection Nr: 1666641.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $15,625.00
Current Penalty: $15,625.00
Issuance Date: 08/09/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/25/2024
Gravity: 10
Report ID: 0728900
Contest Date: 09/05/2023
Final Order: 01/25/2024
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/25/2024 | $15,625.00 | 01/25/2024 | Serious | |
| Penalty | C: Contested | 09/06/2023 | $15,625.00 | 09/05/2023 | Serious | |
| Penalty | Z: Issued | 08/09/2023 | $15,625.00 | 09/05/2023 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.268(b)(7): Approach distances to exposed energized overhead power lines and parts. The employer shall ensure that no employee approaches or takes any conductive object closer to any electrically energized overhead power lines and parts than prescribed in Table R-2: An employee was engaged in telecommunications activities at an existing residential building located at 1002 Avenue B, Bayard, NE 69334, and was exposed to electrocution hazards while working 8-inches from the 2.4Kv line, which is within the 24-inch buffer zone that is prescribed in Table R-2 of this subpart.
Translate