Violation Detail
Standard Cited: 19100269 A04 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1659028.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 10/02/2023 2
Initial Penalty: $15,625.00
Current Penalty: $15,625.00
Issuance Date: 09/13/2023
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order: 10/10/2023
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/10/2023 | $15,625.00 | 10/02/2023 | Serious | |
Penalty | Z: Issued | 09/13/2023 | $15,625.00 | 10/02/2023 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.269(a)(4): Existing characteristics and conditions of electric lines and equipment that were related to the safety of the work to be performed was not determined before work on or near the lines or equipment was started: On or about March 22, 2023, at a remote location behind a personal residence, the existing condition of a transformer was not determined and communicated, exposing employees and contract employees to the hazard of coming in contact with energized parts.