Violation Detail
Standard Cited: 19260451 B02 General requirements.
Inspection Nr: 1478126.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,906.00
Current Penalty: $5,700.00
Issuance Date: 11/06/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 12/28/2020
Gravity: 5
Report ID: 0111500
Contest Date:
Final Order: 12/08/2020
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/08/2020 | $5,700.00 | 12/28/2020 | Serious | |
| Penalty | Z: Issued | 11/06/2020 | $8,906.00 | 12/28/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
1926.451(b)(2): Except as provided in paragraphs (b)(2)(i) and (b)(2)(ii) of this section, the employer did not ensure each scaffold platform and walkway shall be at least 18 inches (46 cm) wide. WORKSITE: The employer did not ensure that each scaffold platform and walkway were at least 18 inches (46 cm) wide where the employee was erecting a form scaffold.