Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1467538.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 07/15/2020 2
Initial Penalty: $4,424.00
Current Penalty: $3,096.80
Issuance Date: 05/28/2020
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC): C
Gravity: 1
Report ID: 0317700
Contest Date:
Final Order: 07/02/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/02/2020 | $3,096.80 | 07/15/2020 | Serious | |
Penalty | Z: Issued | 05/28/2020 | $4,424.00 | 07/15/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: a) Maintenance: Machine specific energy control procedures were not developed or documented for equipment including, but not limited to, the rotomold machine and vacuum forming machine, on or about March 5, 2020. Abatement Certification Required.