Violation Detail
Standard Cited: 19100303 H05 III A General.
Inspection Nr: 1443523.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 03/12/2020 2
Initial Penalty: $13,494.00
Current Penalty: $9,445.80
Issuance Date: 02/24/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 03/30/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/30/2020 | $9,445.80 | 03/12/2020 | Serious | |
Penalty | Z: Issued | 02/24/2020 | $13,494.00 | 03/12/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.303(h)(5)(iii)(A): Entrances to all buildings, rooms, or enclosures containing exposed live parts or exposed conductors operating at over 600 volts, nominal, were not kept locked or while unlocked were not under the observation of a qualified person at all times: On or about November 3, 2019, on north exterior side of the facility where an employee was exposed to electrical hazards after unlocking a switchgear enclosure and testing 13,800 volt exposed phases inside the switchgear without a qualified person being present.