Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1438584.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $13,494.00
Current Penalty: $13,494.00
Issuance Date: 04/09/2020
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 05/27/2020
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 04/24/2020
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/24/2020 | $13,494.00 | 05/27/2020 | Serious | |
| Penalty | Z: Issued | 04/09/2020 | $13,494.00 | 05/27/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s). a) On or about October 17, 2019, in the Maya Structure-I at Shell Deer Park Refinery, the employer failed to ensure all isolating devices needed to isolate the 200# steam system were operated in a manner that isolated the equipment from all energy sources.