Violation Detail
Standard Cited: 19100269 A02 IV Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1425017.015
Citation: 01001A
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $5,304.00
Current Penalty: $9,282.00
Issuance Date: 09/03/2019
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/01/2019
Gravity:
Report ID: 0636900
Contest Date: 09/26/2019
Final Order: 03/13/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 03/13/2020 | $9,282.00 | 10/01/2019 | Other | |
| Penalty | C: Contested | 03/03/2020 | $5,304.00 | 10/01/2019 | Serious | |
| Penalty | Z: Issued | 09/03/2019 | $5,304.00 | 10/01/2019 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.269(a)(2)(iv): The employer did not determine that each employee is complying with all required safety related work practices by regular supervision and Annual inspections. At the facility located at 12567 FM 3430 Vernon, Texas: the employer failed to ensure the employees complied with the required work practices by conducting regular supervision. The employees were exposed to arc flash hazards.
Translate