Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1423074.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,419.00
Current Penalty: $5,209.50
Issuance Date: 01/15/2020
Nr Instances: 2
Nr Exposed: 11
Abatement Date: 02/25/2020
Gravity: 5
Report ID: 0521100
Contest Date:
Final Order: 02/11/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/11/2020 | $5,209.50 | 02/25/2020 | Serious | |
Penalty | Z: Issued | 01/15/2020 | $10,419.00 | 02/25/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.119(d)(3)(i)(B): The employer shall complete a compilation of written process safety information including information pertaining to the equipment in the process including piping and instrument diagrams (P&ID's): At a facility located at 191 W. 28th Avenue, Oshkosh, WI 54902; the employer did not complete a compilation of written process safety information. The P&ID for the anhydrous ammonia system was inaccurate due to: a) P&ID AC04 (Rev. 02) represented a connection to a portion of equipment near compressor AC-100, which had been partially disconnected from the main system. The P&ID inaccurately represented a connections that had physically been disconnected downstream of a tee junction between valves GV-128, GV-132 and GV-160 and upstream of PRV-300.