Violation Detail
Standard Cited: 19100269 M03 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1419422.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,934.00
Current Penalty: $11,934.00
Issuance Date: 12/09/2019
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 01/02/2020
Gravity: 10
Report ID: 0524500
Contest Date: 01/07/2020
Final Order: 12/21/2020
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/21/2020 | $11,934.00 | 01/02/2020 | Serious | |
Penalty | C: Contested | 01/17/2020 | $11,934.00 | 01/02/2020 | Serious | |
Penalty | Z: Issued | 12/09/2019 | $11,934.00 | 01/02/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
1910.269(m)(3)(ii): Deenergizing lines and equipment for employee protection. The employer shall ensure that all switches, disconnectors, jumpers, taps, and other means through which known sources of electric energy may be supplied to the particular lines and equipment to be deenergized are open. The employer shall render such means inoperable, unless its design does not so permit, and then ensure that such means are tagged to indicate that employees are at work. On or about July 14, 2019, the employer did not ensure all means through which known sources of electric energy to be deenergized were open, and did not render such means inoperable with respect to its mobile substation which had been modified by the addition of a maintenance breaker.