Standard Cited: 19100147 C02 III The control of hazardous energy (lockout/tagout).
Inspection Nr: 1370359.015
Citation: 01001A
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $9,282.00
Current Penalty: $4,200.00
Issuance Date: 05/02/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 05/29/2019
Gravity:
Report ID: 0626300
Contest Date:
Final Order: 05/28/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/28/2019 | $4,200.00 | 05/29/2019 | Other | |
| Penalty | Z: Issued | 05/02/2019 | $9,282.00 | 05/29/2019 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(2)(iii): After January 2, 1990, whenever replacement or major repair, renovation or modification of a machine or equipment is performed, and whenever new machines or equipment are installed, energy isolating devices for such machine or equipment was not designed to accept a lockout device: (a) This violation occurred on or about January 09, 2019, at a workplace located at 4647 Bronze Way, Dallas, TX in the production department, where the Combi Case Packer, EQ #21001, DP1080035699 was not retrofitted to accept a lockout device.