Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1364716.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,210.00
Current Penalty: $6,126.00
Issuance Date: 02/13/2019
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 03/01/2019
Gravity: 10
Report ID: 0419400
Contest Date:
Final Order: 03/01/2019
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/01/2019 | $6,126.00 | 03/01/2019 | Serious | |
| Penalty | Z: Issued | 02/13/2019 | $10,210.00 | 03/01/2019 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: (a) Braner Single Loop Slitting Line - On or about December 4, 2018 the employees were exposed to amputation hazards, in that employees were allowed to perform jam clearing operations on equipment such as, but not limited to, Braner Single Loop Slitting Line, without utilizing energy control procedures to prevent accidental startup of the machine.