Violation Detail
Standard Cited: 19261417 O01
Inspection Nr: 1325869.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 12/20/2018
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 12/27/2018
Gravity: 10
Report ID: 0215000
Contest Date: 01/16/2019
Final Order: 05/23/2025
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/23/2025 | $12,934.00 | 12/27/2018 | Serious | |
Penalty | C: Contested | 01/16/2019 | $12,934.00 | 12/27/2018 | Serious | |
Penalty | Z: Issued | 12/20/2018 | $12,934.00 | 12/27/2018 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.1417(o)(1): The equipment was operated in excess of its rated capacity and the operator was required to operate the equipment in a manner that would violate paragraph (o)(1) of this section. Location: a) On fourth floor of the jobsite: On or about 06/25/2018, a Jekko MPK 20 Mini mobile crane was used to hoist curtain wall panels in excess of the capacity of the crane as it was erected and an employee was required to operate a Jekko Mini mobile crane that was used to lift curtain wall panels in excess of its rated capacity.