Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1324885.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,054.00
Current Penalty: $5,500.00
Issuance Date: 11/20/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 01/04/2019
Gravity: 10
Report ID: 0213900
Contest Date:
Final Order: 12/17/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/17/2018 | $5,500.00 | 01/04/2019 | Serious | |
| Penalty | Z: Issued | 11/20/2018 | $9,054.00 | 12/17/2018 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: a) PANDROL USA, LP - Line 1 + 2: The lockout/tagout energy control procedures were not specific for the shear Line 1 + 2 (Die Replacement Procedure). The procedure did not clearly and specifically outline how maintenance employees can control each individual energy source and perform the die replacement operation on the Shear Line 1+2 machine without exposing themselves to the machine hazards while it was ON. Occurred on or about 08/10/2018.