Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1225750.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,310.00
Current Penalty: $2,155.00
Issuance Date: 07/27/2017
Nr Instances: 1
Nr Exposed: 62
Abatement Date: 09/13/2017
Gravity: 5
Report ID: 0522300
Contest Date:
Final Order: 08/10/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/10/2017 | $2,155.00 | 09/13/2017 | Serious | |
| Penalty | Z: Issued | 07/27/2017 | $4,310.00 | 09/13/2017 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: On April 18, 2017, and at times prior to, annual audits to evaluate the effectiveness of the company's machine specific energy control procedures were not completed as required. A review of company's energy control procedures revealed that the procedures were deficient in that the verification step was missing. Energy sources used at the facility include; but are not limited to, electrical, hydraulic, pneumatic and thermal energy.