Violation Detail
Standard Cited: 19100107 G02 Spray finishing using flammable and combustible materials.
Inspection Nr: 1200973.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,431.00
Current Penalty: $3,802.00
Issuance Date: 04/19/2017
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 05/01/2017
Gravity: 1
Report ID: 0523400
Contest Date:
Final Order: 05/04/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/04/2017 | $3,802.00 | 05/01/2017 | Serious | |
| Penalty | Z: Issued | 04/19/2017 | $5,431.00 | 05/01/2017 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.107(g)(2): All spraying areas were not kept as free from the accumulation of deposits of combustible residues as practical, with cleaning conducted daily if necessary: (a) At the top coat paint booth the overspray had accumulated on the inside of the man door and at the edges and threshold of the conveyor exit.