Violation Detail
Standard Cited: 19260403 B02 General requirements.
Inspection Nr: 110699.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,080.00
Current Penalty: $1,540.00
Issuance Date: 02/07/2012
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 02/08/2012
Gravity: 5
Report ID: 0521700
Contest Date:
Final Order: 02/21/2012
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/21/2012 | $1,540.00 | 02/08/2012 | Serious | |
| Penalty | Z: Issued | 02/07/2012 | $3,080.00 | 02/08/2012 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.403(b)(2): installation and use. Listed, labeled, or certified equipment shall be installed and used in accordance with instructions included in the listing, labeling, or certification. a. On or about December 23, 2011 - at the above addressed jobsite, employees used a relocatable power tap for temporary lighting, thereby exposing employees to the hazards associated with electrical shock.