Violation Detail
Standard Cited: 19100269 A03 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1102415.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $12,000.00
Issuance Date: 04/26/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/13/2016
Gravity: 10
Report ID: 0418200
Contest Date: 05/16/2016
Final Order: 03/31/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/31/2017 | $12,000.00 | 06/13/2016 | Serious | |
Penalty | C: Contested | 05/20/2016 | $7,000.00 | 06/13/2016 | Serious | |
Penalty | Z: Issued | 04/26/2016 | $7,000.00 | 06/13/2016 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.269(a)(3)(iii): The contract employer and the host employer did not coordinate their work rules and procedures so that each employee of the contract employer and the host employer is protected as required by this section. a. JBR 3/4 Building - The Georgia Power Company and ABB, Inc. Company did not coordinate their work rules and procedures so that both Georgia Power Company and ABB, Inc. personnel were protected from shock and arc blast/flash hazards while performing circuit buss modification in Frame Cabinets 1, 1A and 7.