Violation Detail
Standard Cited: 19260451 C02 IV General requirements.
Inspection Nr: 1099056.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 01/04/2016
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 01/08/2016
Gravity: 10
Report ID: 0317000
Contest Date:
Final Order: 01/29/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 01/04/2016 | $7,000.00 | 01/08/2016 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(c)(2)(iv): Front-end loaders and similar pieces of equipment were used to support scaffold platforms when they were not specifically designed by the manufacturer for such use. a) Jobsite: Building 5, front - Employees were working from a job-made platform that was not designed by the manufacturer for such use. The job made platform was comprised of wood materials and placed atop the Carterpilar Telehandler to access the roof. Noted on or about 10/5/15.